Replacement of Bridge for Winter Road Crossing - Eabametoong First Nation
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The Proposed Project
Eabametoong First Nation is proposing the installation of a 18 m temporary bridge at a winter road crossing #1 located about 9.5 km east of the community. This crossing has been difficult to flood, freeze and maintain in the beginning of the winter road season, as well as the tail end. The proposed temporary bridge would alleviate these challenges and extend the winter road season, including improving early access to opening and construction of the winter road since it is the first crossing. The scope of work will include:
- Tree clearing and grubbing;
- Demolition of current bridge;
- Removal of topsoil;
- Importing of fill;
- Re-grading.
Infrastructure required includes:
- Aggregates, bearing pads, bridge structure and hardware.
Waste generation:
- No significant waste generation is anticipated. No hazardous waste is anticipated to be generated. Any waste will be disposed of at the local landfill.
Quarry materials to be used:
- A mixture of fine to coarse aggregate materials.
Latest update
November 24, 2025 - Determination of environmental effects of the proposed Replacement of Bridge for Winter Road Crossin on Eabametoong First Nation is no longer required as the Environmental Impact Assessment has been cancelled.
Participate
Key documents
| Document number | Document title | File | Date |
|---|---|---|---|
| 2 | Replacement of Bridge for Winter Road Crossing - Eabametoong First Nation | - | November 24, 2025 |
Contacts
Indigenous Services CanadaHannah Silvaggio, Environment Officer
100 Anemki Place, Suite 101
Fort William First Nation, Ontario P7J 1A5
Telephone: 807-624-5921
Email: hannah.silvaggio@sac-isc.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- Eabametoong First Nation (Ontario)
-
Nature of Activity
- Bridges
-
Assessment Status
Terminated -
Start Date
2025-11-06 -
Proponent
Eabametoong First Nation -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
89986
Nearby assessments
...within 200 kilometres-
East End Subdivision Development - Eabametoong First Nation
Eabametoong First Nation -
Development of 10 Lot Residential Subdivision on Eabametoong First Nation
Eabametoong First Nation -
Neskantaga Community Recreation Centre
Neskantaga First Nation Reserve -
Neskantaga First Nation New Construction of an 8-plex teachers residence
Neskantaga First Nation -
Northern Road Link Project
150km north of the Municipality of Greenstone -
Winter Road Bridge Crossing Construction on Nibinamik First Nation
Nibinamik First Nation -
Electrical Distribution System Upgrades - Marten Falls First Nation
Marten Falls First Nation -
Marten Falls Community Access Road Project
Northern end of Painter Lake forestry road -
Marten Falls Community Access Road Project
Marten Falls -
Regional Assessment in the Ring of Fire Area
Ring of Fire -
Webequie Supply Road Project
Webequie First Nation - Western limit -
Construction of Four Modular Teacherages on Webequie First Nation
Webequie First Nation -
Webequie First Nation - Nursing Station Bulk Fuel Storage Upgrades
Webequie First Nation -
New Fibre Installation
Project Site 5 -
Eagle's Nest Project
Ring of Fire -
Northern Road Link Project
McFaulds Lake area - Northern Limit -
Eagle's Nest Mine Project
Ring of Fire -
Webequie Supply Road Project
McFaulds Lake area - Eastern limit -
Cliffs Chromite Project
McFaulds Lake -
The Elders Lodge at Aroland First Nation
Aroland Elder's Lodge -
Whitesand First Nation - Lot Servicing Project
Whitesand First Nation -
New Fibre Installation
Project Site 3 -
Stormwater Management (SWM) Infrastructure Remediation
Armstrong -
Whitesand Elder's Unit (6-Plex)
Whitesand First Nation -
New Osnaburgh Water Treatment Plant Upgrades
New Osnaburgh -
Wunnumin H1RCI Compound Construction
Wunnumin Lake -
Sachigo Lake First Nation Water Treatment Project
Sachigo Lake First Nation -
Mishkeegogamang Ojibway Nation Broadband Tower Construction
203 Mishkeegogamang -
Wunnumin Lake First Nation Teacherages Project
Wunnumin Lake First Nation -
New Fibre Installation / Upgrade Multiple Towers
Sandy Lake PoP -
New Fibre Installation
Project Site 4 -
New Fibre Installation / Upgrade Multiple Towers
Bearskin Lake PoP -
New Fibre Installation / Upgrade Multiple Towers
Slate Falls PoP -
New Fibre Installation / Upgrade Multiple Towers
Poplar Hill PoP